A. Reasonable Access for Contractor. The Government agrees to permit the Contractor reasonable access to the Property and to place no unreasonable encumbrance upon the free use and enjoyment of the Property by the contractor's personnel, authorized visitors, or any other individuals having a reasonable need to enter the Property.
B. Provision of Utilities and Support Services. The Government shall make available to the Contractor, on a reimbursable basis, the following utilities and services in connection with the Contractor's use of the Property, and the Parties hereto shall enter into a separate agreement concerning the Government's provision of such utilities and services and the Contractor's payment therefor.
Water |
Electricity |
Sewage |
Natural Gas |
Miscellaneous Maintenance |
Entomology Services |
Building Maintenance |
Refuse Collection |
Emergency Ambulance Service |
Hazardous Waste Disposal |
In addition to the foregoing, the Government shall make available to the Contractor, at no cost, the following services in connection with the Contractor's use of the property:
Security |
Fire Protection |
Safety |
Intra-base Mail |
Guard Service (Gate) |
|
C. Parking. The Government agrees to provide the Contractor with ten parking spaces adjacent to the Property as indicated in Schedule B. In addition, the Government will provide the Contractor with access to additional parking in close proximity to the Property.
Installations, Arrangements, Rearrangements, Modifications and Construction. The Contractor may, at its own expense, construct or install any fixed improvements, structural alterations or modifications, or install such capital equipment on the Property as may be necessary to perform its obligations under the Contract. This shall include, but is not limited to, bringing utilities to the Property and providing for the separate metering thereof, making architectural/ structural, mechanical, electrical, or other renovations or alterations to the Property; and, making improvements (including stabilization and drainage) to any open storage areas. The Parties acknowledge and understand, however, that at the expiration or earlier termination of this Agreement, the Contractor may remove any capital equipment that it provided and installed on the Property to perform its obligations under the Contract. However, if the Contractor removes any such capital equipment then the Contractor agrees to restore that portion of the Property vacated by said equipment to a condition such that the Property may once again be used for its original purpose......